Client: Marymount NS
Location:The Rower, Co. Kilkenny
Architect: Bluett & O’Donoghue Architects
Value: €70k
Duration: 6 Weeks
Completed: Aug 2019
Project Features:
- This was s summer works scheme which was carried out during the month of July & August 2019.
- To ensure that the project achieved its programme all the materials had to be pre-ordered to ensure delivery to site once the school had shut for the summer.
- Works also included decoration, making good floors & walls where existing windows were removed.
- The bottom third of the windows was solid panel which required upgrading of the u-value.