Gunnersbury Automotive – Fit Out

Fit-Out

Client: Gunnersbury Automotive
Location: Stadium Business Park, Blanchardstown, Dublin 15
Project Manager: Barry Lyons Designs
Architect: Barry Lyons Design
Value: €340,000
Duration: 16 weeks
Completed: Jul 2017

Project Features:

  • The works entailed the reconstruction and reconfiguration of an existing ware house and office area to accommodate two testing rooms, office area, reception and staff facilities.
  • Mezzanine level extension consisting of hollowcore slab, blockwork, structural steel elements built within the existing unit.
  • Existing concrete stairs and solid supporting blockwork walls removed, new precast stairs and structural steelwork installed.
  • Demolition of existing partitions to facilitate new layout.
  • Replace the existing aluminium door and glazed screen.
  • New tiled floor finish and resin floor to testing room area.
  • New ceiling and wall finishes.
  • Fit-out of testing rooms, which included the
    installation of stainless benches.
  • Mechanical, electrical, compressed air, fire
    alarm, cctv, intruder alarm, etc.

 

Project Details

Gunnersbury Automotive

Fit-Out

Fit-out of Gunnersbury automotive existing warehouse. Reconstruction and reconfiguration of an existing ware house and office area to accommodate two testing rooms, office area, reception and staff facilities.