Archives

Brite:Bill – 7 Grand Canal

Client: BriteBill
Location: 7 Grand Canal, Dublin 2.
Project Manager: RE Project Partners
Architect: Barry Lyons Design
Value: €360,000
Duration: 6 weeks
Completed: Dec 2015

Project Features:

  • Fit-Out of the second floor in two phases, the first phase, which is mainly open plan office, was handed over at the end of week four and the second phase, which included meeting rooms, board room and a canteen which was handed over at the end of week six.
  • Partitions were mainly, curved glazed screens (W2W) with a design vinyl graphic.
  • There was a considerable amount of curved plasterboard ceilings to compliment the curved walls.
  • Floor coverings to a raised access floor followed an intricate pattern of shapes and colours.
  • Full mechanical, electrical and data installations
  • Full fit-out including all specialist joinery for reception counter, canteen and tea station.
  • This was an excellent project, which had an excellent client, project manager, designer and contract team, which resulted in the project being handed over on time, within budget and most importantly to the high standards expected.

 

*This project was not carried out by RMCC but our management team where all involved in this project

CPL HQ – Percy Place, Dublin 2

Client: CPL
Location: 2nd & 3rd Floor, Investment House, Percy Place.
Project Manager: RE Project Partners
Architect: Kennedy Woods
Value: €880,000
Duration: 8 weeks
Completed: Nov 2014

Project Features:

  • This 1600 sqm fit-out was carried out over two phases with the second phase lagging the first by two week. Phase 1 was Floor 3 and Phase 2 was Floor 2.
  • Complete strip out of the existing 2nd & 3rd floors, ceilings, walls, floor covering, electrical and mechanical services.
  • An intricate design which had to accommodate open plan office, ten interview rooms, four meeting rooms, high volume canteen, training rooms, board room and reception area.
  • Partitions included, glazed, fire rated and non-fire rated.
  • The existing raised access floor remained but considerable modifications were required to accommodate the new layout and floor finishes.
  • Existing toilet blocks on both floor completely revamp, with new tiling, vanity units and sanitary ware.
  • Complete replacement of the existing finishes, floor, wall ceiling, etc. throughout the building
  • Full mechanical, air conditioning and ventilation system installed. New electrical installations, data, lighting, power, fire alarm etc.
  • The boardroom was fitted out using bespoke joinery to accommodate the interactive tv’s and video conference.
  • Work carried out within a live building.

 

* This project was not carried out by RMCC but our management team where all involved in this project

Naas Credit Union – Monread

Client: Naas Credit Union
Location: Monread Shopping Centre, Naas
Project Manager: RE Project Partners
Architect: BDA & BLD
Structural Engineer: MPA
Value: €320,000
Duration: Design & Planning 4 months | On Site – 8 weeks
Completed: July 2013

Project Features:

  • Full design responsibility from conception, planning and construction
  • Installation of new mezzanine floor and construction of office spaces
  • Construction of loans offices to ground floor
  • Full mechanical, electrical and sprinkler installations
  • Full fit-out including all joinery for banking counters
  • Work carried out in a live Shopping Centre.

 

*This project was not carried out by RMCC but our management team where all involved in this project

Naas Credit Union – Main St. Naas

Client: Naas Credit Union
Location: Monread Shopping Centre, Naas.
Project Manager: RE Project Partners
Architect: Barry Lyons Designs
Structural Engineer: Punch
Value: €417,000
Duration: 4 weeks
Completed: Jan 2015

Project Features:

  • The bank closed on Christmas eve for a shutdown period of 3 ½ weeks and reopen fully refurbished on the third Friday in January. Works commenced over the Christmas holidays.
  • Complete strip out of the existing banking hall.
  • Considerable amount of structural modification to all for the removal of bulky concrete columns which were replaced with steel columns.
  • Complete replacement of the existing finishes, floor, wall ceiling, etc. throughout the building.
  • New automated entrance lobby.
  • Refurbishment of the existing office area through the building.
  • Construction of loans offices to ground floor
  • Full mechanical, electrical and sprinkler installations
  • Full fit-out including all joinery for banking counters
  • Work carried out on a busy main street without on-site storage, parking, etc..

 

*This project was not carried out by RMCC but our management team where all involved in this project